Ongoing Work
- Popout Works continue with the steel installed and the glazing
framed out
- Foyer Roof sheeting installation
- Door frame installation and wall rough works
- Wall sheeting
- Installation of ceiling hangers
- Roof sheeting and cladding
- Removal of temporary bracing removed
- Façade restoration, painting, rendering and brick repair
- Main hall steel, roofing and cladding
Upcoming Work
Lower rooms interior finishes
Further structural steel
Mezzanine level slab installation
- Sheeting, wall and floor finishes
- Services to be installed
- Façade restoration and door installation
- Installation of louvers and doors
- Back wall cladding
|