Project Updates: November, 2011
4 November, 2011
AREA |
UPDATE
|
INDUSTRIAL PAVILION |
New Work
- Infrastructure installation for first suspended slab
Ongoing Work
- Bulk and detail excavation, concrete pour for columns and
footings
Upcoming Work
- Concrete pour to continue for columns and footings while
awaiting the first suspended slab to be laid
|
LITTLE WATER STREET INFRASTRUCTURE ENABLING
WORKS |
Ongoing Work
- Removal of Agriculture Hall and Dog Pavilion
Upcoming Work
- Preliminary soil works for stormwater and sewer lines
- Construction of stormwater intake structure
|

Gregory Terrace and Ekka Plaza facade |

Site Works |

Removal of Agricultural Hall |

Removal of Dog Pavilion |

Panoramic |
11 November, 2011
AREA |
UPDATE
|
LITTLE WATER STREET INFRASTRUCTURE ENABLING
WORKS |
New Work
- Preliminary soil works for stormwater and sewer lines
Ongoing Work
Upcoming Work
- Site preparation and foundation piling for stormwater inlet
structure
|
_250x188.jpg) |
_250x188.jpg) |
18 November, 2011
AREA |
UPDATE
|
LITTLE WATER STREET INFRASTRUCTURE ENABLING
WORKS |
New Work
- Compaction ground works for machinery
- Foundation piling for stormwater infrastructure
Ongoing Work
Upcoming Work
- Piling for further stormwater infrastructure
- St Pauls Terrace stormwater connection works
- Alexandria Street stormwater works
- Foundation piling around stormwater inlet structure
- Culvert works to commence
- Erection of hoarding to Jubilee Hotel boundary
|
_250x188.jpg)
|
_250x188.jpg) |
23 November, 2011
Preliminary soil works for stormwater and sewer
lines